Drainage and waterproofing on capping of the landfill of Saint Brès
Drainage et imperméabilisation de la couverture du centre de stockage de déchets de Saint-Brès
Résumé
Objectives of the Saint-Brès landfill capping are waterproofing, water drainage and earth retaining. Slopes on cover reach 66% with length superior to 10 m. Geosynthetic solution is composed from bottom to top of a protective geotextile, a drainage geocomposite industrially associated to a textured 8/10 mm polyethylene film to increase the stability of the system and a earth retaining geogrid. Geocomposite has been designed with Lymphéa® software to drain a rain of 266 mm/day. A polyethylene film was welded on site to increase the waterproofing of the capping.
La réalisation de la couverture du centre de stockage de déchets ménages et assimilés (CSDMA) de Saint-Brès a pour objectifs l'imperméabilisation, le drainage des eaux de pluies et la retenue de la terre végétale. La couverture possède des talus pentés à 66 % avec des rampants supérieurs à 10 m. Le complexe géosynthétique est composé de bas en haut par un géotextile antipoinçonnant, un géocomposite de drainage associé en usine à un film polyéthylène 8/10 mm texturée en sous-face pour augmenter la stabilité du dispositif et une géogrille de retenue des terres. Le géocomposite a été dimensionné hydrauliquement avec le logiciel Lymphéa® pour drainer une pluie de 266 mm/jour. Le film du géocomposite a été soudé sur site pour garantir une imperméabilisation optimale de la couverture.